Master Time Line & Work Plan

Auxiliary Engine Crankshaft Replacement & Installation (Marine Gen-Set)

Target Duration: 2 Months (8 Weeks)

Status: Ready for Class Re-Inspection & Normal Operation

Equipment / Unit
Auxiliary Engine / Diesel Gen.
Scope of Work
Crankshaft Replacement
Compliance Standard
Maker Standard & Class
Target (End of Month 2)
Normal Operational Load Test

1. Interactive Execution Schedule Matrix (8-Week Gantt Chart)

Work Breakdown Structure (WBS) Details PIC / Team MONTH 1 (Dismantle, Inspect & Bedding) MONTH 2 (Installation, Assembly & Comm.)
W1W2W3W4W5W6W7W8
Phase 1: Preparation, Safety LOTO & Initial Dismantling (W1)
1.1 System isolation (LOTO), oil/coolant draining & fuel purgingEng Team
1.2 Removal of piping, wiring harness, turbocharger, intercooler & exhaustEng Team
Phase 2: Dismantling Top & Moving Components (W2)
2.1 Removal of Cylinder Head, valve train assembly & rocker armsEng Team
2.2 Extraction of Piston assembly, Con-Rod, and Cylinder Liner inspectionEng/Workshop
2.3 Removal of Flywheel, generator coupling, damper & timing gear trainEng/Workshop
Phase 3: Old Crankshaft Lifting & Engine Block Inspection (W3)
3.1 Main Bearing Caps removal & rigging old crankshaft outRigging Team
3.2 Crankcase cleaning, NDT inspection & Line Boring check on saddle blockQC / Class
Phase 4: New Crankshaft QC & Main Bearing Prep (W4)
4.1 Unboxing, cleaning, dimensional & hardness QC check of new CrankshaftQC / Maker
4.2 Installation of new Lower Main Bearing Shells & oil clearance dry-fit checkLead Spec.
4.3 Rigging & lowering new Crankshaft to Engine BedRigging Team
Phase 5: Main Bearing Tightening & Initial Deflection (W5)
5.1 Install Upper Bearing, Main Bearing Caps & hydraulic bolt tensioningLead Spec.
5.2 Thrust Bearing axial clearance measurement & Initial Cold Crankshaft DeflectionQC / Supt
Phase 6: Piston/Con-Rod Reassembly & Generator Alignment (W6)
6.1 Install new Con-rod bearings, Piston & Con-rod assy, torque tighteningEng Team
6.2 Timing Gear, Flywheel, Damper installation & Laser Alignment to AlternatorAlign Spec.
Phase 7: Final Assembly, Lube Flushing & Pre-Commissioning (W7)
7.1 Cylinder Head installation, valve lash setting, fuel injection timing, accessoriesEng Team
7.2 Lube Oil System flushing, filter change, new oil & coolant fillingEng Team
7.3 Final pre-lubrication check, 360° engine barring & Deflection Re-checkChief Eng
Phase 8: Sea Trial, Load Testing, Class Re-Inspection & Handover (W8)
8.1 Initial Running (Uncoupled/No-load), monitor temp & lube pressureCommissioning
8.2 Step Load Test (25%, 50%, 75%, 100%, 110% Overload) & Paralleling sync checkSupt / Elect.
8.3 Hot Crankshaft Deflection Test, Final Class Surveyor Inspection & Sign-offClass / Supt
8.4 Operational handover (Handover to Normal Sea Service Operation)Chief Eng

2. Technical Details & Quality Control Checkpoints

Week 1: Preparation, Safety & Initial Dismantling
  • Implementation of Permit to Work (Hot/Cold Work & Enclosed Space) and electrical/piping LOTO.
  • Total draining of sump tank, oil waste disposal according to MARPOL regulations.
  • Labeling of all instrumentation sensor cables and water/fuel piping connections.
QC: LOTO isolation verification & component marking
Week 2: Dismantling Moving Components
  • Removal of head units, rocker arms, push rods, stored on cylinder-numbered racks.
  • Piston & con-rod assy extraction, visual check of crown condition, ring grooves, and liner bore.
  • Flywheel & generator coupling removal using certified hydraulic pulling jacks.
QC: Cylinder liner ovality & piston ring groove thickness
Week 3: Old Crankshaft Lifting & Engine Bed Check
  • Gradual opening of main bearing caps from center to ends to prevent stress relaxation.
  • Rigging old crankshaft out of the engine room using approved lifting beams.
  • NDT Inspection (Dye Penetrant / Magnetic Particle) & line boring on saddle block engine.
QC: Line Bore Alignment Report & Class Surveyor survey
Week 4: New Crankshaft Prep & Bedding
  • Verification of manufacturer certificate (Mill/Class) and pin/journal dimensions.
  • Cleaning of internal oil passages on new crankshaft with diesel & compressed air.
  • Installation of new lower bearing shells, lubrication with assembly lube, and lowering crankshaft.
QC: Main Journal dimension verification & Plastigauge check
Week 5: Main Bearing Tightening & Initial Deflection
  • Tightening main bearing cap bolts using hydraulic jack pump according to maker pressure.
  • Thrust bearing end-play (axial clearance) check using dial gauge indicator.
  • Data recording of Cold Crankshaft Deflection at BDC, Port, Top, Starboard.
QC: Deflection values within maker tolerance (< 0.05 mm)
Week 6: Component Reassembly & Generator Alignment
  • Installation of new con-rod bearings, assembly of piston & con-rod to crankshaft journal.
  • Installation of timing gear train and verification of valve/fuel pump timing index marks.
  • Laser alignment of Engine-Generator coupling (radial & axial offset alignment).
QC: Engine-Generator Alignment Report (Tol < 0.05 mm)
Week 7: Final Assembly, Lube Flushing & Pre-Start
  • Installation of cylinder heads, exhaust/intake manifolds, injectors & valve clearance calibration.
  • Engine oil flushing for a minimum of 24 hours with fine mesh bypass filter.
  • Filling fresh lube oil, priming lubrication system, 360° manual engine turning free of resistance.
QC: Lube oil cleanliness analysis & Crankshaft deflection
Week 8: Sea Trial, Class Re-Inspection & Handover
  • Initial start-up without load (10 min) then shutdown to open crankcase and check bearing temp.
  • Step running: 25% (1 hr), 50% (2 hrs), 75% (2 hrs), 100% (4 hrs), 110% Overload (1 hr).
  • Hot Deflection measurement, genset parallel load synchronization test.
MILESTONE: Class Sign-off & Handover
🎯 Success Criteria & Normal Operation Requirements (Target End of Month 2)
1. Mechanical Parameters:
  • Cold & Hot Deflection conform to maker limits.
  • Lube Oil pressure is stable (4.0 - 5.5 bar).
  • Main/big-end bearing temperatures normal (< 75°C).
2. Electrical & Load Parameters:
  • Capable of sustaining 100% continuous full load.
  • Governor response is stable during sudden load transitions.
  • Parallel synchronization & load sharing is balanced.
3. Administration & Legality:
  • Complete Overhaul & Load Test Protocol / Report.
  • Approval & endorsement from Classification Society Surveyor.
  • Engine is ready for normal operation for official voyages.
Technical Executor / Workshop
( Lead Engine Specialist )
Head of Marine Overhaul Team
Ship Owner / Management
( Chief Engineer / Tech. Supt )
Vessel Management Representative
Classification Society
( Class Surveyor )
Classification Society Official