Master Time Line & Work Plan (2-Month)

General Overhaul (Major OH) Marine Main Engine

Target Duration: 2 Months (8 Weeks)

Method: STANDARD TRACK (1 Shift - Safe)

Equipment / Unit
Main Engine NINGBO G6300ZCA
Scope of Work
Major Overhaul & Sea Trial
Working System
1 Shift (Regular 8 Hours/day)
Spare Part Status
100% Available Onboard
✅ ADVANTAGES - Standard Track Schedule Characteristics: Highly recommended. Work is performed more sequentially, ensuring much more thorough Quality Control (QC). It provides a very safe daily buffer time in case of severe mechanical constraints (such as worn bolts or jammed liners during extraction). Saves on overtime costs.

1. Execution Schedule Matrix (8-Week Gantt Chart)

Phase & Work Details (WBS) Duration (Weeks) MONTH 1 (Dismantling & Inspection) MONTH 2 (Reassembly & Commissioning)
W1W2W3W4W5W6W7W8
Phase 1: Preparation & External Accessories
Safety isolation, fluid draining. Removal of external piping, manifolds, engine guards, Turbocharger and Intercooler. Week 1
Phase 2: Top Component Dismantling
Removal of head covers, rocker arm mechanisms, extraction of Injectors and Fuel Injection Pumps (FIP). Lifting of 6 Cylinder Heads to workshop. Week 2
Phase 3: Liner & Piston Dismantling
Extraction of Pistons & Con-Rods. Installation of hydraulic pullers to extract Cylinder Liners. Manual scale cleaning of water jacket. Week 3
Phase 4: Crankshaft Inspection & Workshop
Lowering of Main Bearing caps. Measure Crankshaft Deflection & clearance. Head servicing, nozzle & FIP calibration ongoing in workshop. Week 4
Phase 5: Bottom Core Assembly (Bedding)
Installation of new Main Bearing shells, hydraulic tightening of main cap bolts. Checking block alignment & Cold Crankshaft Deflection. Week 5
Phase 6: Liner & Piston Reassembly
Installation of Cylinder Liners with new O-rings. Assembling new piston rings, inserting Piston & Con-rod units, tightening big-end bolts. Week 6
Phase 7: Top Component Installation
Installation of 6 Cylinder Head units, push rods, valve lash adjustment. Reinstallation of Turbocharger, cooler, manifolds, FIP, and injection lines. Week 7
Phase 8: Flushing, Running & Sea Trial
Lubrication system flushing 24-48 hours. Manual turning checks (barring). Dock trial, Step Load test, concluding with official Sea Trial. Week 8

2. Technical Activity Details (Weekly)

Week 1: Preparation & Externals
Safety isolation, draining of lubricating and cooling fluids. Removal of all external piping components, air/exhaust manifolds, engine guards, and lifting of the Turbocharger and Intercooler from the engine bed.
Week 2: Top Dismantling
Removal of head covers and rocker arm mechanisms. Extraction of Injector units and Fuel Injection Pumps (FIP). Lifting of 6 Cylinder Head units gradually to the workshop area for reconditioning.
Week 3: Liner & Piston Dismantling
Extraction of all Pistons along with Connecting Rods. Installation of heavy-duty hydraulic pullers to extract the Cylinder Liners. Followed by manual scale cleaning of the engine block's water jacket.
Week 4: Crankshaft Inspection
Lowering of Main Bearing caps. Measurement of initial Crankshaft Deflection indicators before full dismantling, and clearance checks. Simultaneously, nozzle and FIP calibration work is ongoing in the workshop.
Week 5: Bottom Core Assembly
Installation of new Main Bearing shells, followed by tightening of main cap bolts using a hydraulic pump according to NINGBO manual standards. Inspection of block alignment and Cold Crankshaft Deflection.
Week 6: Liner & Piston Reassembly
Reinstallation of the cleaned Cylinder Liners using new seals/O-rings. Assembling new piston rings onto the piston crowns, inserting the Piston & Con-rod units into the block, and tightening the big-end bearing bolts.
Week 7: Top Component Installation
Reinstallation of the 6 Cylinder Head units and push rods, followed by valve lash clearance adjustment. Reassembling the Turbocharger, intercooler, all manifolds, FIP units, and high-pressure injection piping lines.
Week 8: Sea Trial & Sign-Off
Cleaning circulation (flushing) of the lubrication system for 24-48 hours. Manual turning checks (barring). Initial running test (Dock trial), followed by Step Load testing at the pier, and concluding with an official operational Sea Trial at sea with Class.
Overhaul Executor
( Lead Engine Specialist )
Head of Marine Team
Ship Owner / Management
( Chief Engineer )
Vessel Management
Classification Society
( Class Surveyor )
Class Society Official