General Overhaul (Major OH) Marine Main Engine
Method: STANDARD TRACK (1 Shift - Safe)
| Phase & Work Details (WBS) | Duration (Weeks) | MONTH 1 (Dismantling & Inspection) | MONTH 2 (Reassembly & Commissioning) | ||||||
|---|---|---|---|---|---|---|---|---|---|
| W1 | W2 | W3 | W4 | W5 | W6 | W7 | W8 | ||
| Phase 1: Preparation & External Accessories | |||||||||
| Safety isolation, fluid draining. Removal of external piping, manifolds, engine guards, Turbocharger and Intercooler. | Week 1 | ||||||||
| Phase 2: Top Component Dismantling | |||||||||
| Removal of head covers, rocker arm mechanisms, extraction of Injectors and Fuel Injection Pumps (FIP). Lifting of 6 Cylinder Heads to workshop. | Week 2 | ||||||||
| Phase 3: Liner & Piston Dismantling | |||||||||
| Extraction of Pistons & Con-Rods. Installation of hydraulic pullers to extract Cylinder Liners. Manual scale cleaning of water jacket. | Week 3 | ||||||||
| Phase 4: Crankshaft Inspection & Workshop | |||||||||
| Lowering of Main Bearing caps. Measure Crankshaft Deflection & clearance. Head servicing, nozzle & FIP calibration ongoing in workshop. | Week 4 | ||||||||
| Phase 5: Bottom Core Assembly (Bedding) | |||||||||
| Installation of new Main Bearing shells, hydraulic tightening of main cap bolts. Checking block alignment & Cold Crankshaft Deflection. | Week 5 | ||||||||
| Phase 6: Liner & Piston Reassembly | |||||||||
| Installation of Cylinder Liners with new O-rings. Assembling new piston rings, inserting Piston & Con-rod units, tightening big-end bolts. | Week 6 | ||||||||
| Phase 7: Top Component Installation | |||||||||
| Installation of 6 Cylinder Head units, push rods, valve lash adjustment. Reinstallation of Turbocharger, cooler, manifolds, FIP, and injection lines. | Week 7 | ||||||||
| Phase 8: Flushing, Running & Sea Trial | |||||||||
| Lubrication system flushing 24-48 hours. Manual turning checks (barring). Dock trial, Step Load test, concluding with official Sea Trial. | Week 8 | ||||||||