Marine Auxiliary Engine Top Overhaul, Spare Part Supply & Repair
Status: Re-Inspection Ready & Normal Operation
| Work Breakdown Structure & Procurement (WBS) | PIC / Team | MONTH 1 (Inspection & Procure.) | MONTH 2 (Workshop & Parts Arrival) | MONTH 3 (Assembly & Class) | |||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| W1 | W2 | W3 | W4 | W5 | W6 | W7 | W8 | W9 | W10 | W11 | W12 | ||
| Phase 1: Preparation, Safety LOTO & Top Component Dismantling (W1-W2) | |||||||||||||
| 1.1 Safety permit, electrical/piping LOTO, oil & coolant draining | Eng Team | ||||||||||||
| 1.2 Removal of exhaust/intake manifold, sensor wiring & piping | Eng Team | ||||||||||||
| 1.3 Dismantling of Cylinder Heads, Rocker arm assy & Push rods | Eng Team | ||||||||||||
| 1.4 Removal of Fuel Injectors, Fuel Pumps & Turbocharger | Eng Team | ||||||||||||
| Phase 2: Initial Measurement, Assessment & Part Procurement (W2-W6) | |||||||||||||
| 2.1 Cleaning, wear calibration & formulation of deficit Part List | QC / Supt | ||||||||||||
| 2.2 Issuance of Purchase Orders (PO) for spare parts | Procurement | ||||||||||||
| 2.3 Fabrication / delivery / logistics supply process of new parts | Logistics | ||||||||||||
| Phase 3: Component Reconditioning at Partner Workshop (W4-W7) | |||||||||||||
| 3.1 Cylinder Head overhaul: decoking, hydro-test, valve lapping | Workshop | ||||||||||||
| 3.2 Fuel Injection Pump calibration & Nozzle testing | Fuel Spec. | ||||||||||||
| 3.3 Chemical cleaning of Air Cooler & Turbocharger repair | Workshop | ||||||||||||
| Phase 4: New Spare Part QC & Onboard Inspection (W7-W8) | |||||||||||||
| 4.1 Receipt of spare parts, material certificate & visual QC | QC / Supt | ||||||||||||
| 4.2 Visual inspection of upper liner bore & piston decoking | Eng Team | ||||||||||||
| Phase 5: Top Engine Component Reassembly (W8-W9) | |||||||||||||
| 5.1 Install new Cylinder Head gaskets, Head units & torque | Eng Team | ||||||||||||
| 5.2 Install Rocker arms, set valve lash clearance | Lead Spec. | ||||||||||||
| 5.3 Installation of Fuel Pumps, Injectors, Turbo & Cooler assy | Eng Team | ||||||||||||
| Phase 6: Manifold Installation, Piping & System Flushing (W10) | |||||||||||||
| 6.1 Installation of intake/exhaust manifolds, reconnect piping | Eng Team | ||||||||||||
| 6.2 Lube oil & cooling system flushing, filter element change | Eng Team | ||||||||||||
| Phase 7: Pre-Comm. & Full Load Test & Handover (W11-W12) | |||||||||||||
| 7.1 Pre-lubrication test, 360° barring, initial uncoupled start | Chief Eng | ||||||||||||
| 7.2 Step Load Testing (25%, 50%, 75% load) | Comm. | ||||||||||||
| 7.3 Full Load (100%) & Overload test (110%), paralleling | Class/Supt | ||||||||||||
| 7.4 Class Surveyor re-inspection, Handover Protocol sign-off | Class/Supt | ||||||||||||