Master Time Line & Work Plan (3-Month)

Marine Auxiliary Engine Top Overhaul, Spare Part Supply & Repair

Target Duration: 3 Months (12 Weeks)

Status: Re-Inspection Ready & Normal Operation

Equipment / Unit
Marine Auxiliary Diesel Engine
Scope of Work
Top Overhaul & Sparepart Supply
Compliance Standard
Maker Manual & Class (BKI/IACS)
Target (End of Month 3)
Full Load & Normal Sea Service

1. Interactive Execution Schedule Matrix (12-Week Gantt Chart)

Work Breakdown Structure & Procurement (WBS) PIC / Team MONTH 1 (Inspection & Procure.) MONTH 2 (Workshop & Parts Arrival) MONTH 3 (Assembly & Class)
W1W2W3W4W5W6W7W8 W9W10W11W12
Phase 1: Preparation, Safety LOTO & Top Component Dismantling (W1-W2)
1.1 Safety permit, electrical/piping LOTO, oil & coolant drainingEng Team
1.2 Removal of exhaust/intake manifold, sensor wiring & pipingEng Team
1.3 Dismantling of Cylinder Heads, Rocker arm assy & Push rodsEng Team
1.4 Removal of Fuel Injectors, Fuel Pumps & TurbochargerEng Team
Phase 2: Initial Measurement, Assessment & Part Procurement (W2-W6)
2.1 Cleaning, wear calibration & formulation of deficit Part ListQC / Supt
2.2 Issuance of Purchase Orders (PO) for spare partsProcurement
2.3 Fabrication / delivery / logistics supply process of new partsLogistics
Phase 3: Component Reconditioning at Partner Workshop (W4-W7)
3.1 Cylinder Head overhaul: decoking, hydro-test, valve lappingWorkshop
3.2 Fuel Injection Pump calibration & Nozzle testingFuel Spec.
3.3 Chemical cleaning of Air Cooler & Turbocharger repairWorkshop
Phase 4: New Spare Part QC & Onboard Inspection (W7-W8)
4.1 Receipt of spare parts, material certificate & visual QCQC / Supt
4.2 Visual inspection of upper liner bore & piston decokingEng Team
Phase 5: Top Engine Component Reassembly (W8-W9)
5.1 Install new Cylinder Head gaskets, Head units & torqueEng Team
5.2 Install Rocker arms, set valve lash clearanceLead Spec.
5.3 Installation of Fuel Pumps, Injectors, Turbo & Cooler assyEng Team
Phase 6: Manifold Installation, Piping & System Flushing (W10)
6.1 Installation of intake/exhaust manifolds, reconnect pipingEng Team
6.2 Lube oil & cooling system flushing, filter element changeEng Team
Phase 7: Pre-Comm. & Full Load Test & Handover (W11-W12)
7.1 Pre-lubrication test, 360° barring, initial uncoupled startChief Eng
7.2 Step Load Testing (25%, 50%, 75% load)Comm.
7.3 Full Load (100%) & Overload test (110%), parallelingClass/Supt
7.4 Class Surveyor re-inspection, Handover Protocol sign-offClass/Supt

2. Technical Details & Quality Control Checkpoints

Phase 1 (W1-W2): Preparation & Top Dismantling
  • Implementation of electrical/piping LOTO, draining crankcase oil and fresh cooling water.
  • Dismantling of exhaust/intake manifolds, rocker arm assemblies, pushrods, and all Cylinder Heads.
  • Extraction of all Fuel Injectors, injection pumps (FIP), turbocharger unit, and charge air cooler.
QC: Instrumentation cable labeling & hole protection
Phase 2 (W2-W6): Assessment & Part Procurement
  • Visual inspection & wear measurement of valves, valve seats, guides, nozzles, and upper liner bore.
  • Preparation of Purchase Orders (PO) for certified maker/OEM spare parts.
  • Monitoring logistics lead time for spare part delivery (gasket kits, valve sets, injector nozzles).
QC: Verification of part numbers against Maker Part Book
Phase 3 (W4-W7): Reconditioning at Partner Workshop
  • Cylinder head servicing: hydro-test for cracks, valve seat renewal, valve lapping & guide replacement.
  • Fuel injection pump (FIP) test-bench calibration & new injector spray pattern testing.
  • Chemical cleaning of air cooler (intercooler), turbocharger rotor dynamic balancing.
QC: Cylinder Head Pressure Test & Nozzle Spray Report
Phase 4 (W7-W8): Parts Arrival QC & Pre-Assembly
  • Physical inspection of all arrived spare parts, verification of maker material batch certificates.
  • Carbon deposit cleaning (decoking) on piston crowns and upper cylinder liner walls.
QC: Incoming Parts Inspection Checklist & thickness verified
Phase 5 (W8-W9): Top Engine Component Reassembly
  • Cylinder head installation with new gasket kits, progressive bolt tightening per manual torque specs.
  • Rocker arm & pushrod installation, intake/exhaust valve lash clearance calibration.
  • Installation of tested injectors, calibrated fuel pumps, turbocharger, and overhauled air cooler.
QC: Head Bolt Tightening Torque Log & Valve Lash Clearances
Phase 6 (W10): Manifold, Piping & System Flushing
  • Exhaust manifold, charge air ducting, and high-pressure (HP) fuel pipe installation.
  • Lubrication cleaning circulation (oil flushing), replacement of oil, fuel & air filters.
  • Filling fresh lube oil, fresh coolant, and air bleeding of the fuel supply system.
QC: Pipe connection tightness verification, free of leaks
Phase 7-8 (W11-W12): Comm., Sea Trial & Handover
  • Initial start-up without load (15 min no-load test), monitoring oil pressure and water temp.
  • Step load testing via load bank / vessel load: 25%, 50%, and 75% capacity.
  • 100% full load testing (continuous running) & 110% overload testing with load sharing.
MILESTONE: Class Re-Inspection & Operational Sign-off
🎯 Success Criteria & Normal Operation Requirements (Target End of Month 3)
1. Engine Mechanical Parameters:
  • Balanced cylinder combustion compression.
  • Lube pressure is stable per maker standards.
  • Exhaust gas temperatures are evenly distributed.
  • Free from oil, cooling water & exhaust gas leaks.
2. Electrical & Gen-Set Performance:
  • Passed 100% continuous load & 110% overload tests.
  • Governor response is stable during load fluctuations.
  • Frequency (50/60 Hz) & voltage are stable.
  • Automatic synchronization & load sharing normal.
3. Administration & Legality:
  • Injector calibration & head service reports complete.
  • Sea Trial / Load Test Protocol is fully signed.
  • Approved & endorsed by Classification Society Surveyor.
  • Auxiliary engine is officially in normal operation.
Overhaul Contractor / Executor
( Lead Marine Overhaul Team )
Mechanical & Workshop Specialist
Ship Owner / Management
( Chief Engineer / Tech. Supt )
Vessel Management Representative
Classification Society
( Class Surveyor )
Classification Society Official